Phase 3 Public Realm

Meeting: 08/03/2018 - Policy and Resources Committee (Item 174)

174 Phase 3 Public Realm pdf icon PDF 59 KB

Additional documents:

Minutes:

Mrs Fran Wallis, the Local Economy Project Officer, presented a report proposing to enter into a Section 278 agreement with Kent Highways in order to carry out Phase 3 of the Public Realm regeneration scheme.

 

Mrs Wallis confirmed that since the report had last been taken to the Committee, six tenders had been received and there was no shortfall in funding due to the value of the tenders received.

 

The two options that Mrs Wallis presented to the Committee were that the Committee could instruct the Monitoring Officer to enter into a Section 278 agreement or do nothing. The do nothing option would result in the scheme not progressing as a Section 278 agreement was required for the scheme to progress.

 

RESOLVED:

 

That delegated authority is given to the Head of Mid Kent Legal Services to enter into a s278 agreement with Kent County Council for the Phase 3 Public Realm Highway Works.

 

Voting: Unanimous