Contact: Karen Luck
01622 602743
Items
No. |
Item |
1. |
High Level Bridge Improvements and Western Tow Path Accessibility PDF 84 KB
Additional documents:
Decision:
1.
That the Business Case and Project Initiation
Document, as attached at appendices A and B to the report of the
Assistant Director of Regeneration and Cultural Services, be agreed
and the project formally created. That
the £300,000 of Section 106 money be spent on improvements to
the Bridge and the accessibility of the tow path in accordance with
the Supplemental Deed to the Section 106 agreement relating to the
former Trebor Bassett site (now
Scotney Gardens).
2.
That delegated authority be given to the Project
Executive (the Assistant Director of Regeneration and Cultural
Services) to determine the specific work and division of
expenditure on the Bridge and the towpath at the appropriate
project stage boundary.
|